ITER Council milestone #50 successfully achieved . WELL DONE to ALL

March 28TH 2020

Passing an ITER Council milestone is always an achievement. Passing this milestone at this moment is much more than that: it is a demonstration that, despite the constraints imposed by the public health context, the ITER Organization, the European Domestic Agency and their contractors are determined to keep moving forward and to remain on schedule.

ITER Council milestone #50, which was successfully achieved two days ahead of schedule late on 28 March, is of considerable significance for the project, as it opens the way for the launch of the machine assembly phase.

The milestone consisted in demonstrating that the heavy lift cranes could successfully travel between the Assembly Hall and the Tokamak Building in order to deliver components to the Tokamak pit.

Three actions were required: first, the completion of the crane hall structure; second, the removal of the temporary wall separating the buildings; and finally, the verification of the overhead crane load path in the Tokamak Building.

The last operation, both spectacular and delicate, required validating the full 170-metre-long runway of the double bridge crane—from the entrance of the Assembly Hall, all the way to the opposite end of the newly created crane hall and back.

It was a display of Titans, with no less than 1,000 tonnes of steel and concrete test loads attached to the giant hoists of the bridge crane.

 

VIDEO 

 

Initiated at 8:00 a.m., the operation lasted well into the night and was only considered completed when the crane and its loads had returned to the Assembly Hall and were secured.
By then Saturday had turned into Sunday, but 31 March—the official target for ITER Council milestone #50*—was still 48 hours away.

The crane and its loads moved slowly, taking long pauses at strategic locations: at the “seismic link” between the two buildings, at the threshold of the Tokamak Building, over the protruding lid of the Assembly Pit …

All the while, metrology systems were monitoring the deflections that the loads were causing to the runway beams and steel pillars—essential information for validating the crane hall’s structure and achieving the milestone.

With the temporary wall between the Assembly Hall and Tokamak Building removed, one could take in, for the first time, the full theatre of future assembly operations—a huge open space that even dwarfs the 20-metre-high vacuum vessel sector sub-assembly tools.

It was an awesome view that conveyed the unique size, complexity and beauty of ITER.

 

WELL DONE TO ALL IN THIS VERY DIFFICULT TIME

 

 

Source 

Join a dynamic group!
we are always on the lookout for new talents!
Reel, we hire all over the world

REEL Norway Receives TMS Award for Innovation in Aluminum Production

REEL Norway team has been very proud to receive The Minerals, Metals & Materials Society award at TMS Annual Meeting

Alba and REEL Alesa Celebrate Ship Unloader’s 25-Year Upgrade Success

Ship Unloader Upgrade Success: Alba & REEL ALESA Achieve Milestone in Operational Excellence!

REEL at ARABAL International Aluminium Conference 2023 Riyadh

We are present at ARABAL 2023 in Riyadh and available to address any of your needs. potlines, anode production, ports

Alumina Ship Loader En Route to Queensland Alumina Limited

Alumina Ship Loader En Route to Queensland Alumina LimitedOur brand new Alumina ship loader is ready and on its way to o