Early 2021, in order to meet the Safety requirements requested by the ASN to EDF, Framatome designed the support collar to be installed around each of the three points in the main primary circuit of the Flamanville EPR reactor.
The solution was validated by the ASN and led Framatome to order the supply of these ollars from REEL in October 2021. Their manufacture was a major challenge for the maintenance of the commissioning schedule for the new Flamanville power plant.
Source SFEN: SFEN briefing note of 20/10/2021
It took REEL only 11 months to manufacture and deliver the parts in accordance with the initial schedule, while meeting numerous requirements in terms of manufacturing quality in the context of an extremely tight deadline.
REEL is proud of its teams for having successfully taken up this challenge, in close collaboration with FRAMATOME and EDF, but also for having been able to contribute again to the activities of the FLAMANVILLE 3 plant.
Clamps installed on the site of Flamanville 3
REEL is proud of its teams for having successfully taken up this challenge, in close collaboration with
Indeed, REEL has already supplied all the equipment allowing the loading and unloading of fuel assemblies in the fuel building as well as in the reactor building.
To find out more :
REEL Norway team has been very proud to receive The Minerals, Metals & Materials Society award at TMS Annual Meeting
Ship Unloader Upgrade Success: Alba & REEL ALESA Achieve Milestone in Operational Excellence!
We are present at ARABAL 2023 in Riyadh and available to address any of your needs. potlines, anode production, ports
Alumina Ship Loader En Route to Queensland Alumina LimitedOur brand new Alumina ship loader is ready and on its way to o